• Project Title: Eltham College Turberville Building

  • location: Grove Park Road | Mottingham | LONDON

  • Completed: January 2019

  • Client: Eltham College

  • Project Manager: Bristow Johnson

  • Quantity Surveyor: Bristow Johnson

  • Architect: Levitt Bernstein

  • Structural Engineer: Morgan Tucker

  • Services Engineer: Crofton

  • Project Value: £10million

The Eltham College project included the demolition of the existing and surrounding buildings to allow for a new build teaching facility, including a sixth form centre.

Works included piled foundations, cross wall construction, twin wall precast concrete frame, structural steelwork and exposed fair faced concrete classrooms. The works also comprised external landscaping and were carried out adjacent to the live school environment.

Contact us

Would you like to discuss a project? Are you interested in working with us?
Please do not hesitate to contact us.

More Education projects